UPDATE: Caltrans has notified the City that the traffic signal change at Willow Road and Bayfront Expressway, initially scheduled for Wed., Jan. 13, has been postponed. Further information about the new date/time for this work will be released as soon as it becomes available.
ORIGINAL MESSAGE:
Facebook traffic mitigation and drainage improvements are nearing completion at the intersection of Willow Road and Bayfront Expressway. As part of the project to add a third right turn lane from Willow Road toward the Dumbarton Bridge, the traffic signal has been modified and new traffic signal poles have been installed. Weather permitting,
Caltrans is scheduled to perform the traffic signal switch over Wednesday, Jan. 13, starting at 10 a.m. The operation should take about four hours with traffic delays expected during the work.
Menlo Park Police will assist with the traffic control to minimize impacts as much as possible.