Although Jack Lyle Park is highly utilized by several field user groups and the general public, there are currently no permanent restroom facilities available for public use. This project involves engaging the neighboring community in developing a conceptual design, then constructing permanent public restrooms at Jack Lyle Park.

Project background 


Read about the project history.
Jack Lyle Park restroom project

Restroom construction detailsJack Lyle Park Restroom Project

The Jack Lyle Park restroom will be pre-fabricated offsite and then placed in its final location.  See the below figures for details of the pre-fabricated restroom floor plan and its exterior.

Current Status


Date  Activity
May 22, 2018 City Council approved awarded of construction contract
Early September 2018 Start of underground utility construction