This project will utilize slurry seal, overlay, and reconstruct treatments to resurface deteriorating streets throughout the city.


Planned Activities
(tentative, subject to change)
Sep 15, Mon Chilco Street: paving
Florence Lane: pavement grinding
Menlo Avenue (east bound): pavement section repairs
Sep 16, Tue Menalto Avenue: paving
Menlo Avenue (west bound): pavement section repairs
Sep 17, Wed Florence Lane: paving
Sharon Park Drive: pavement grinding
Sep 18, Thu Menlo Avenue: paving
Sharon Park Drive: pavement grinding
Sep 19, Fri Sharon Park Drive: pavement grinding
Sep 22, Mon Sharon Park Drive: pavement grinding
Sep 23, Tue Sharon Park Drive: paving
Sep 24, Wed Sharon Park Drive: paving
Sep 25, Thu Sharon Park Drive: paving

Past Activities
Sep 05, Fri Chilco Street: pavement section repairs
Coleman Place: pavement section repairs
Marcussen Drive: pavement section repairs
McKendry Drive: pavement section repairs
Sep 04, Thu Chilco Street: pavement section repairs
Klamath Court: pavement section repairs
Oakdell Drive: pavement section repairs
Trinity Court: pavement section repairs
Sep 03, Wed Bay Road (north bound): pavement grinding and section repairs
Sep 02, Tue Bay Road (north bound): pavement section repairs
Sep 01, Mon HOLIDAY: No work
Aug 29, Fri Bay Road: pavement section repairs
Aug 28, Thu No work planned
Aug 27, Wed Bay Road: pavement section repairs
Ringwood Avenue: pavement section repairs
Aug 26, Tue Bay Road (south bound): pavement grinding
Aug 25, Mon Alma Street: paving
Aug 20, Wed Alma Street: pavement section repairs
Laurel Street: pavement section repairs
Aug 15, Fri Laurel Street: utility prospecting
Aug 14, Thu Garwood Way: paving
Glenwood Avenue: paving
University Drive: paving
Aug 13, Wed Chestnut Drive: pavement grinding
Crane Street: pavement grinding
Glenwood Avenue: pavement grinding
University Drive: pavement grinding
Aug 12, Tue Chestnut Drive: pavement section repairs and grinding
Crane Street: pavement section repairs and grinding
Garwood Way: pavement section repairs and grinding
University Drive: pavement section repairs and grinding
Aug 11, Mon Encinal Avenue: pavement section repairs
Garwood Way: pavement grinding and section repairs
Glenwood Avenue: pavement section repairs
Aug 8, Fri Fremont Street: paving
Week of
July 21
Alma Street: curb ramp construction
Menalto Road: curb ramp construction
2008, Jun 17 The City Council awards the construction contract to Pavex/Graniterock and approves an overall construction project budget of $4,160,000. To offset a portion of the cost, the Council also authorizes a request to the state for $500,062 of Proposition 1B funds.
Contract Award Staff Report  |  Proposition 1B Staff Report
2008, Jun 3 Construction bid proposals are due to the City. Upon review of the submitted proposals, Graniterock -- doing business as Pavex, is determined to be the lowest responsible bidder with a bid of $3,295,880.
Plan Holders List  |  Bid Summary
2008, May 7 The construction bid period begins with the local advertisement of "Notice to Contractors."
Notice to Contractors


Copyright ©2008 :: City of Menlo Park :: All Rights Reserved