This project is intended to further develop a previous study and identify areas where sidewalks should be installed for pedestrian safety along Santa Cruz Avenue between the limits of Olive Street and Johnson Street (see the map at the bottom of this page). The study will include more detailed engineering design alternatives including drainage, potential parking impacts, landscape impacts, etc.

On the lower portion of this page are illustrations of some preliminary concepts that can be used as a basis of discussion as the study progresses toward identifying a preferred plan (click on a graphic for an enlarged view). The illustrations do not necessarily represent all conditions at every point along the study segment.

Planned Activities
Presentation of refined conceptual plans to the Transportation Commission.
Presentation of the refined conceptual plans and a recommendation by staff and the Transportation Commission of a preferred plan to the City Council.

Past Activities
2008, Aug 19 Community meeting to review preliminary conceptual plans.
> Burgess Recreation Center, Room 112, 7:00 p.m. - 9:00 p.m.
2008, Jul 22 Community meeting to review topographic survey and to discuss concerns and
suggestions concerning possible sidewalk alignments.
> Burgess Recreation Center, Room 112, 7:00 p.m. - 9:00 p.m.
2008, Jul 14 An information survey is mailed to 5,200 residents who live in the vicinity of Santa Cruz Avenue. Nearly 500 completed surveys are returned.
Survey Results: Graphs | Tabulated Data & Comments
2008, Apr 01 The City Council authorizes a budget amendment and a contract with BKF Engineers.
Staff Report

Existing Condition

    (Click on Image for Larger View)

Alternative 1

    New vertical curb and gutter on both sides of the road. New sidewalk on the north side only.

Alternative 2

    New sidewalk and vertical curb and gutter on both sides of the road with public utility easements.

Alternative 3

    New sidewalk and vertical curb and gutter on both sides of the road with sidewalk easements.

Alternative 4

    New sidewalk and vertical curb and gutter on both sides of the road with shoulder encroachments.