|
|
QuickLinks Emergencies History Jobs City Calendar


Capital Improvement Program

City of Menlo Park
701 Laurel Street
Menlo Park, CA 94025

Tel. 650.330.6740
Fax 650.327.5403

Project Coordinator
Jennifer C. Ng, PE

Consultants

  • Infrastructure Engineering        Corporation (IEC)
  • Jones and Stokes
  • Verde Design, Inc.



  • Documents
    Kennedy-Jenks Final
    Feasibility Evaluation
    (Large File - 9 MB)

    Metcalf and Eddy Water System Evaluation Report
    (Large File - 17.5 MB)

    May 28, 2008 Powerpoint Presentation
    May 28, 2008 Meeting Transcript


    Related Links
    Menlo Park Municipal Water District (MPMWD)
    District Map

    Supplemental Emergency Water Supply Project

    The City of Menlo Park Municipal Water District (MPMWD) serves about one third of the City's residents. All of its water is purchased from the San Francisco Public Utilities Commission (SFPUC) and is delivered via four pipelines; two serve the Sharon Heights neighborhood and a City reservoir in the upper elevation zone of the City, and two serve the geographic area of the City roughly north and east of El Camino Real (lower zone). Currently, no water emergency storage facility exists in this lower zone. If the SFPUC pipeline to this zone were disrupted by an earthquake or other emergency, this area of the City would be left without water until the pipeline could be repaired.

    To address this issue the City began considering options in the late 1990s. Staff and consultants recommended, and the City Council agreed, that construction of an underground reservoir, a backup groundwater well and a pump station should be considered. Four sites were evaluated based on cost and constructability. Of those sites, Seminary Oaks Park was chosen as the best location. The City is beginning to evaluate the environmental impacts and develop a preliminary design of the new facilities.

    After construction, the City will install new park facilities on top of the reservoir location. The City wants the neighbors to help re-design the new park facilities and is holding community meetings to seek input from neighbors. During construction, which is expected to take about 18 months, the City will work with consultants and contractors to minimize construction-related impacts (noise, vibration, dust, traffic control, safety) to the greatest extent possible.

    Planned Activities
    2008, Jul 1 The City Council will be updated on the project and the additional options to be evaluated.
    Staff Report
    2008, Fall Second Community Meeting


    Past Activities
    2008, May 28 Open House, Presentation, and Community Meeting at the Burgess Recreation Center
    2007, Sept IEC submitted a technical memo analyzing various site-plan alternatives at Seminary Oaks Park for construction of an underground reservoir. It included basic assumptions and design criteria for evaluating the water distribution system with respect to a new reservoir. IEC recommended a minimum storage requirement of 3.5 million gallons. This included maximum single day demand plus fire flow.
    2007, June Discussions with West Bay Sanitary District began regarding placement of the reservoir to ensure compliance with State Health Regulations.
    2007, May Consultant TRC submitted a summary of the results of ground water monitoring. From April 2006 through May 2007 ground water varied between 23 and 29 feet below the ground. A progress meeting was held with IEC and City engineering staff to review issues regarding placement of the reservoir and compliance with State Health Regulations.
    2007, Mar IEC submitted a Fatal Flaw Analysis which concluded that the Seminary Oaks site was large enough and the ground water table was low enough to allow a subsurface reservoir to be built.
    2006, Oct City Council approved an agreement with Infrastructure Engineering Corp (IEC) for engineering consultant services to begin preliminary design.
    Staff Report  |  Meeting Minutes
    2005, Dec City Council approved Seminary Oaks Park as the preferred site for further study, site analysis, geotechnical evaluations, preliminary design and public outreach for a new reservoir and well.
    Staff Report  |  Meeting Minutes
    2005
    Jan thru Dec
    Kennedy/Jenks Consultants submitted the Final Feasibility Evaluation of Menlo Park/East Palo Alto Joint Reservoir Facility and Alternative Water Supply. Nine sites were considered, but the joint reservoir was found not to be feasible. The Evaluation concluded that a single reservoir and well for Menlo Park would be feasible.
    2003, Aug Council approved an agreement with Kennedy/Jenks Consultants to study various water storage alternatives and the possibility of a joint-use reservoir with the City of East Palo Alto.
    Staff Report  |  Meeting Minutes
    2000 Metcalf and Eddy report finalized evaluating and modeling the Menlo Park Municipal Water District system. The report identified the need for an emergency storage facility and secondary source of water supply.


    Copyright ©2008 :: City of Menlo Park :: All Rights Reserved