Project Description

The State Department of Water Resources requires water districts to update their water plans every five years. Referred to as an Urban Water Management Plan (UWMP), it discusses water supply for the next 20 years and addresses water resources, supply, demand, reliability, shortages and distribution. Public input on the plan is encouraged.

Current Project Status

In January 2011, the City contracted with Winzler & Kelly to write its 2010 Urban Water Management Plan (UWMP) and to update its Water Shortage Contingency Plan (WSCP). A draft was published in May and a 30-day public comment period followed. Comments were incorporated into the final draft which was approved by City Council on June 14, 2011.

Project Goals

This project developed a complete 2010 UWMP which addresses changing conditions related to water availability and usage and ensures reliability of water for the next 20-years.  The WSCP was also updated to re-evaluate and improve the program for equitable distribution of water during a shortage.  The final documents contained recommendations for planning, program operation, and maintenance of the water distribution system.

Planned Activities

 

None


Past Activities

2011, July

UWMP delivered to California Department of Water Resources, San Mateo County and other recipients.

   

2011, May & June

30-day public comment period.

   

2011, June 14

Final draft approved by City Council.

   
2011, May 13 Draft Posted for Public Review.
   
2011, April 5 City Council Information Item: UWMP Update and Baseline Determination.
   
2011, Feb 8 City forwarded background documents to Consultant.
   

2010, Nov 18

Five proposals were submitted, opened and reviewed.  Decision was made to begin contract negotiations with Winzler & Kelly.

   

2010, Oct 26

A Request for Proposal was distributed to 28 consultants for development of the 2010 Urban Water Management Plan and update to the Water Shortage Contingency Plan.

 

 